At a Glance:

 

CDOT #IM0703-291

Location: I70 & Hwy 58

Contractor: Ames Construction Co.

Size: 37,000sf of retaining wall

Completion: 2008

 

 

 

 

 

 

 

 

Landmark Boulder

Location: Boulder, CO

Contractor:  Wyatt Construction

Size: 7900sf Permanent Soil Nails

         3900sf Temporary Shoring

         8000sf Modular Block Wall

Completion:  2008

 

Vail Mountain View

Location:  Vail, CO

Contractor:  WVC Company

Size: 9000sf Soil Nail & Shotcrete

         Temporary Shoring

Completion:  2008

 

Howelsen Place

Location:  Steamboat Springs, CO

Contractor:  Calcon Constructors

Size:  1100lf Micropile Temp Shoring

          & Foundation Micropiles

Completion:  2007

 

Andesite Point

Location:  Crested Butte, CO

Contractor:  Mericana

Size:  22,750sf Permanent Soil Nail

          & Shotcrete Retaining Wall

Completion:  2008

 

Lion Square Lodge North

Location:  Vail, CO

Contractor:  J.L. Viele

Size:  Design & Construct 9535sf of

          Soil Nail & Shotcrete Shoring

Completion:  2008

 